Permitting Capability

Permitting Experience

  1. The DCCR CSO Tunnel Program, a 2.6 billion-dollar program, in the District of Columbia is being implemented to reduce combined sewer overflows. We have processed well over 1,800 permit applications. We work closely with reviewers within DDOT and other District agencies, such as Department of Energy and Environment (DOEE), utility companies, such as PEPCO and Washington Gas, and third-party reviewers. In addition, we coordinated major engineering design submittal reviews with DDOT reviewers and third-party reviewers for DCCR CSO tunnel projects during the design phase to make sure that the designs can be permitted during the permitting phase to meet the project schedule under the DDOT AWI Program with Ch2M team.
    DC Clean Rivers CSO Tunnel Program
  2. Our permit specialists have also processed DDOT public space permit applications for this 250-300 million dollars CSX Virginia Avenue Tunnel Project. We have processed about 200 DDOT public space permit applications for this project. As a part of the permitting support effort, we coordinate the permitting effort with the D/B team to identify priority permit applications and coordinate the permitting process with the CH2M project management team.
    CSX Virginia Avenue Tunnel Project
  3. SZPM is currently developing permitting processes and procedures for each type of permits required from all permitting agencies as well as all reviews from reviewing agencies for DC Water projects in the District under this permitting contract.
    DC Water DCFA #482 - Permit Support Services with RK&K
  4. Program Management Contract with CH2M team.
    DDOT Anacostia Waterfront Initiative (AWI)
  5. Permitting support and utility coordination services with Arcadis.
    WSSC PCCP Water Transmission Main Replacement
  6. Permitting support services with Arcadis. Permitting support services with Pure Technology.
    DC Water DCFA #485 IDIQ for Condition Assessment of Large Diameter Water Mains and Major Sewers
Other Permitting Experience

  • ​​U.S. Army Corps of Engineers (ACOE) - dredging and fill permit at intracoastal waterway for a pipeline project
  • Federal/state DEP – injection well permits for wastewater treatment plant effluent disposal (34 million gallons per day, 3500-ft deep)
  • District Department of Consumer and Regulatory Affairs (DCRA) – DC Water projects
  • State DEP – wastewater treatment plant upgrades, capacity rerate, and pipeline projects
  • State DOT – for pipeline work within ROW, state road crossings, etc.
  • CSX – railroad crossing
  • Electrical Utilities – power line relocations for force main installations
  • Gas companies – emergency generation facility for wastewater treatment facilities
  • Health Departments – water main projects
  • Building permits – Local cities, counties
  • Land disturbance permits
  • Golf course operator – pipe line through golf course
  • Park Authority – project coordination